Teichmann Namibia successfully completed Phase A, the first 110 km’s of the 245 km upgrade to the road from Gobabis to Aranos in Namibia. In 2020 we are currently working on Phase B, the final 135 km, upgrading the existing gravel road to black top standard.
Current contract at a glance:
Scope of Works: Upgrade 135km of existing gravel road to black top standard
Total length of Phase B: 135km
Total volume of gravel to be moved and processed: 2 300 000m³
Gravel deviation to be constructed along entire length
Natural gravel base course of crushed stone/borrow material in 60/40 blend respectively
Surfacing: Cape seal (19mm chip and spray with two layers of slurry)
Contract period: 24 months
Contracts Director: Alan McKinney